Utility-scale and C&I battery projects delivered by UEH across Australia, with
standalone BESS in development across the National Electricity Market.
A 5 MW / 11 MWh LFP battery energy storage system in Naracoorte, South Australia, delivered end to end by United Energy Hub as EPC contractor, from design to energisation in 10 months.
UEHu2019s role: design and engineering, procurement, civil works and installation,
HV/LV electrical, protection, 33 kV grid connection and commissioning.u00a0
Power capacity
Energy capacity
Grid connection
Design to energisation